Macquarie Tower Tops Out

Macquarie Tower Tops Out

Macquarie Tower reaches its tallest milestone to date, as it reaches the top level of this impressive mixed-use development.

Just below the top it’s a bustling time with The Hive Academy child care centre progressing, Allianz fitting out its new offices, and Pulse Mining is on site preparing its new headquarters.

In the residential levels, apartments are coming along with framing and sheeting taking place. Kitchens and bathrooms will follow closely behind in the coming weeks and months. 

The team have worked hard all the way to the end, and have some brilliant stats to share....

  • 10500m3 of fill removed from site
  • Installed approximately 550 tonnes of reinforcing steel
  • Approx. 8400 m3 of Hunter Readymixed Concrete
  • Over 1,300 agitator trucks delivered to site
  • 1,025 Hunter Precast panels installed
  • Delivered by 300 trucks
  • 21 suspended concrete deck pours in 12 months GF to level 16
  • Completed structural construction of the development.


For more information on Macquarie Tower, click here.